Client: Ranno E., project manager of a real estate developer. Building: Near Rotermann Salt Warehouse, Central City.
1. Coarse debris and packaging material: packaging cardboard, protective film and construction waste went into one container, the removal time of which was set on the morning of the first day, and 80 m² of protective film was removed from the elevator doors, window glass and the floor of the commercial premises.
2. HEPA vacuuming of all surfaces: The H13 HEPA filter vacuum cleaner with a 3-meter extension wand cleaned the light tops, ventilation grilles, window sills and stair railings on all five floors of the two stairwells.
3. Wet cleaning and finishing: the large-format tiles of the stairwells, elevator entrances and parking floor elevator entrances were wet-washed, the calcium residues on the 36 m² windows of the business area were softened with an acidic agent before washing, and the door handles, elevator buttons and mailbox fronts were disinfected last.
4. In the written summary of the works, the site supervisor noted 11 construction defects on the floor plan, among them 3 scratched window panes.
Price: Post-construction cleaning, 460 m² × €2.60 = €1,196.00; protective film removed from glass and floor, 80 m² × €0.50 = €40.00; window cleaning, 36 m² × €1.20 = €43.20; removal of the construction waste container, 1 × €160 = €160.00; inspection of the site after repair €0; the travel charge at the Tallinn site is €0. Total without VAT €1,439.20, VAT 22% €316.62, total with VAT €1,755.82.
Duration: 2 working days for three cleaners, of which the finishing washing of shop windows took 1 hour 48 minutes on the second day, job no. 2 717 (2024).
Result on the site: The general contractor corrected the 11 construction errors noted in the summary, and the developer handed over the house to the first residents 5 days after cleaning.